Dive Transient:

  • Some development on the Harbor Bridge in Corpus Christi, Texas — the place work was shut down over security issues earlier this summer season — will resume as early as subsequent week, following the decision of one in all 5 key design points. 
  • Texas DOT and contractor Flatiron/Dragados introduced throughout a press tour of the jobsite on Oct. 28 that the redesign of the delta frames has been accredited, based on the Corpus Christi Caller Occasions. The brand new designs included further metal on elements of the frames.
  • Initially scheduled for completion in 2020, the almost $1 billion undertaking is now tentatively set to complete in 2025, Texas DOT stated, and a extra exact timeline will likely be launched when the remainder of the design points are resolved. Nonetheless excellent are alleged design flaws in the primary cable-stayed portion of the bridge and the place cranes will likely be positioned whereas it’s being constructed. 

Dive Perception:

In early August 2022, Texas DOT warned that the undertaking had design flaws so vital that “the bridge would collapse beneath sure load situations” if it have been completed per the present design. It cited a 2020 unbiased evaluation that had recognized a collection of design and development flaws, in addition to the contractors’ “lack of responsiveness” to its issues first raised in April. 

Flatiron/Dragados, nevertheless, stated its design work is “absolutely compliant with the phrases of the great improvement settlement” and questioned why Texas DOT had allowed a lot of the bridge to be constructed although it had recognized issues a lot earlier.

An Arup-CFC three way partnership took over in July 2020 the design and engineering work FIGG Bridge Engineers had began. Texas DOT had fired FIGG after a Nationwide Transportation Security Board report discovered the engineer’s designs have been the “possible trigger” in a 2018 pedestrian bridge collapse at Florida Worldwide College in Miami that killed six individuals.

Texas DOT paused work on the Harbor Bridge in July 2022, and in mid-August, it issued a discover of default and threatened to fireplace the contractors if a number of key components weren’t reworked. By the top of the month, Flatiron/Dragados dedicated “to do no matter must be achieved” to tackle the company’s issues and full the undertaking, and Texas DOT stated exchanges grew to become extra productive after that. The three way partnership has proposed options to the protection points and the Texas DOT is presently reviewing them.

Calculating the prices

Flatiron/Dagados can pay for the redesigns and repairs, however the remaining price of the changes isn’t but identified. Throughout a Sept. 6 listening to, Texas DOT Govt Director Marc Williams stated the company plans to train extra oversight on tasks just like the Harbor Bridge sooner or later.

The undertaking entails constructing the bridge construction and about 6.5 miles of roadway on U.S. 181, which spans the Corpus Christi Ship Channel off of the Gulf of Mexico. Along with being safer for customers than the previous Harbor Bridge, officers stated the better clearance on the brand new span will enable bigger ships to move by and allow the Port of Corpus Christi to compete with different Gulf Coast deep water ports.

As of the press convention Friday, the authorized ramifications triggered by Texas DOT’s August discover of default to Flatiron/Dragados are nonetheless in impact, that means the company can take away the contractor with out issuing one other discover. Per an Oct. 6 settlement between the 2 events, it’s going to stay in place till Flatiron/Dragados initiates work to deal with the design issues to Texas DOT’s satisfaction.



Supply hyperlink

By